Friday, December 9, 2011

conc work

the upper terrace is being poured this afnoon, we are having good weather the last couple of days.
next week we can install the roof and start work on the stair and railings.




here's a couple of views of the design's model




Wednesday, December 7, 2011

Leigh dec

doors and windows are up, electrical, hvac ducts and plumbing are in place. on the exterior the lath was done earlier this week, today its ready for stucco, the scratch layer should be done today.



afetr the holyday break, cabinetry will be ready, drywall and fixtures as well. the stuff sticking out of the floor are the kitchen island utilities.
After the stucco is done, the set of windows on the front facade will have a larger element with louvers, combining both upper and lower windows as one big element.



the finish color on the tall volume to the right should be of a light color to resemble the white stucco on the neighboring white structure to the right.